2016-Sep-20 NYSERDA decision on funding (yes), not announced yet There's a LINAC16 paper on CBETA, can use as a citation for CBETA Add Steve Full to e-mail list Georg etc. will possibly create CBETA e-mail list on "cornell-l" machine CBETA abstracts/papers have to be sent to Dejan and Georg Linac's admin limit is 76MeV, enough cooling for 73MeV, after accounting for de-tuning/microphonics 50MeV maximum (with fewer solid state amplifiers) "We should see money in October" (if the contract is signed quickly) Chris Mayes has a spreadsheet of topics for Thursday each week Currently 10% contingency under $25M (labour+capital add up to $22.xM, with no contingency baked into line items except ~$500k for scope adjustment under project management) They want 30% contingency i.e. 25/1.3 = $19.23M actual cost Bunch of other stuff 0.5(DC gun)+0.75(RF)+0.25(cryo labour)+0.5(shielding cost escalation) = $2M needs to be added in future revision